Set Plan as Closed
Explanation
The Close Sustainability Plan activity is used to indicate that all
activities related to the plan are completed and no further actions are
required.
Prerequisites
- User Access: The user must have “Full Access” to the plan.
- Plan Status: The plan must be in "Completed" status.
System Effects
- As a result of this activity: The plan is no longer editable, and it
is not possible to change its status or create snapshots.
- Only activities related to visualization can continue.