This activity is used to enter the quality inspection results for a production schedule. What to inspect on a specific production schedule operation is defined in the control plan manufacturing connected to the production schedule by part. Inspection of lot/batch and/or serial tracked parts are not supported.
Use the Enter and View Results dialog to enter (or view) the inspection results. This dialog can be accessed by clicking Enter and View Results button in the Analysis Result Lines section on the Analysis Result page. The Analysis Result page can be accessed by creating an analysis in the Production Line Management, Production Schedule Progress Point Reporting, Production Schedule Receipt, Production Schedule by Line or Production Schedule by Part page. It can also be accessed by clicking Analysis Details in the Production Line Management, Production Schedule Progress Point Reporting, Production Schedule Receipt, Production Schedule by Line or Production Schedule by Part page.
The inspection results are entered in the Enter and View Results dialog. If the analysis contains several data points, it is possible to navigate between them by clicking Previous and Next.
To complete the analysis result for a data point click Complete either in the Enter and View Results dialog or in the Analysis Result Lines section on the Analysis Result page. Once the line is in the Complete status, the results cannot be edited.
If Real Time SPC has been activated for a data point, then Real Time SPC chart will be automatically updated and validated when the data point is set to the status Complete.
When all data points for an analysis have been reported, you can change the status of the analysis result to Confirmed. Either click Confirm Registered Result in the Enter and View Results dialog or Confirm Analysis on the Analysis Result page. It is also possible to confirm analysis result from the Production Schedule Analyses page, by clicking Confirm Registered Result for one or multiple analyses.
To manually create a new control chart, if SPC is activated in the control plan, click Create SPC Chart in the Analysis Result Lines section on the Analysis Result page. To print a report of results for the Variable data type items, click Print Data Sheet in the Analysis Result Lines section on the Analysis Result page. To print the results of the analysis, click Print Analysis Results on the Analysis Result page.
This activity contains a security checkpoint which can be activated by an administrator. With an activated security checkpoint on a function you will have to authenticate yourself again in order to fulfill the function. Additionally, whenever a security checkpoint is successfully passed a security checkpoint log is written, creating an audit trail of what is done.
This activity has the following prerequisites:
As a result of this activity, analysis results have been entered, completed, and confirmed. Once an analysis has been confirmed, the results cannot be edited.