This activity is used to update the calculated periodic progress values to the selected Project Forecast. This can be achieved by performing the Update Project Forecast command on the Work Recording Summary page.
When the selected Project Forecast is created using the Copied with Details option, the selection of Cost or Revenue options and the levels will not be allowed to change.
The Calculated Date of the Schedule of Work Production should be within the range of the Cut Off Date of your selected Project Forecast
The Progress % of the selected Project Forecast Item lines will be updated based on the Work Record progress.