Explanation

This activity is used to log work progress, which can be performed on the Work Recording page. This can be done by specifying the completed quantity via the fields; Current Quantity, Cumulative Quantity, or Progress %.

Backdated work recording can be performed by manually specifying the Record Date.

Work completed should not exceed the Item Quantity unless the Over Production Allowed option is selected for your item line.

Item Plan Start and Item Plan Finish dates will indicate the date range within which work recording is expected to be completed.

The person assigned to do the work recording can be specified as the Responsible Person.

If needed, the status can be demoted through the Schedule of Work Production Management page.

Prerequisites

Item line should be in Released or Started status.

System Effects