Explanation

Forecast lines contain the amounts retrieved from cost/revenue elements and occasionally by code parts if code parts have been defined as mandatory in code part demands for cost elements. A project forecast may consist of a number of lines for each cost/revenue element.

Project Forecast lines contain the amounts retrieved from cost/revenue elements, and occasionally from code parts, if these have been defined as mandatory in Code Part Demands for cost elements in the Project Setup Parameters page. A project forecast may consist of multiple lines for each cost or revenue element.

This activity is used to create forecast lines. These lines can be created in both the Project Forecast and EAC Workbench pages. Once created, the lines can be reviewed and confirmed in the Project Forecast.

Prerequisites

System Effects