Copy Activity

Explanation

There are two ways to add activities to a subproject: create new activities or copy an existing activity.

During copying, if an existing activity is selected, this activity is used as the activity to copy. If a sub project is selected, this sub project is designated as the sub project to which the new activity will belong.

Prerequisites

A sub project exists with activities that can be copied.

System Effects