Import Demand Planning/Customer Schedule Forecasts

The purpose of importing forecasts from demand planner or customer schedules is to provide an alternative to the manual entry of forecasts for master scheduled level 1 parts and MRP planned spare parts. The manual process can be repetitive and tedious, especially for the forecasts that must be maintained weekly. Importing previously generated forecasts, either online or in the background greatly reduces the quantity of time that you spend entering and maintaining forecasts. With this option, you may choose to maintain a forecast manually, before or after the forecast has been imported.

On the Master Schedule Level 1 Part page, under Master Scheduling Planning Data, there are two toggles: Include in Import Customer Schedule and Include in Import Demand Planning Forecast. These toggles allow you to determine whether a specific Master Schedule Level 1 part should be included or excluded from the Import Customer Schedules job or from the Import Demand Planning Forecasts job, respectively.  

Once the import process is completed, you can analyze its results in the appropriate Master Scheduling or MRP pages. You can view the imported forecasts and can change or delete some or all of them according to the needs. You will have to manually alter imported forecast at times to make the forecast more realistic according the current production and market conditions. For example, the forecasts generated by the demand planner and imported to master scheduling cannot be achieved based on the production capacities or the imported forecasted quantities itself that does not match with the current market fluctuations.

The following are key terms that relate to the import process:

Term Definition
Begin Date and End Date The dates that you enter in the Import Demand Planning Forecasts or Import Customer Schedules to indicate the time span for which you want to import forecasts.
Start Date and End Date The dates that appear in Exported Forecasts to indicate the period covered by forecasts.
Delivery Date/From Date and To Date The dates that appear in Customer Schedule to indicate the period covered by forecasts.
Starting Date and Ending Date The dates that the system uses to calculate the imported forecast quantity.

You import forecasts into Master Scheduling or MRP from Exported Forecasts or Customer Schedule. The Import Demand Planning Forecasts or Import Customer Schedules lets you specify the import parameters where you defined the date range for which the imports of forecasts should take place. The results appear in the appropriate MRP or Master Scheduling page.

Several factors determine the time period for which the forecasts are imported. For a spare part in MRP, you can specify this period by defining the Begin Date and End Date in Import Demand Planning Forecasts for Spare Parts. Same naming is used in Import Customer Schedules which uses to import customer schedule forecasts to Master Scheduling Level 1. It is also possible to enter the start and end dates into the Date Range field in Import Demand Planning Forecasts as well.

For a level 1 part in Master Scheduling, you can indicate whether the forecasts inside the planning time fence (PTF) need to be updated or not from the toggle Copy Forecast Inside Planning Time Fence in the Import Demand Planning Forecasts assistant. If you do not request to copy forecasts inside the planning time fence (PTF), the forecasts within the planning time fence (PTF) will not be changed and the system will import forecasts outside of the planning time fence (PTF) based on the imported date range. If you enable the Copy Forecast Inside Planning Time Fence, then the system will import forecasts outside the demand time fence (DTF) and eventually forecasts inside the planning time fence (PTF) will be updated.

The Exported Forecasts or Customer Schedule includes columns for Start Date and End Date. The dates in these columns may be different from the Begin Date and the End Date that you entered in Import Demand Planning Forecasts or Import Customer Schedules. When this occurs, the system calculates the forecast quantity using the formulas shown below.

How the Imported Forecast Quantity is Calculated

The imported forecast quantity depends on the following factors:

The formula for determining the imported forecast quantity is as follows:

Forecast quantity imported = Forecast or budget quantity / n, where n is the number of days (working days for MRP spares) between the Start Date/From Date and End Date/To Date specified in Exported Forecasts or Customer Schedule.

For Master Scheduling Level 1 parts, the imported forecast proportion does not depend on the manufacturing calendar and does not differ from the working and non-working days included in the given date range. Instead, it will forecast the actual proportion of the imports by dividing the actual forecasted quantity of the period from the number of days defined by the Start Date and End Date of the given Date Range and insert it on the particular Begin Date depending on the forecast distribution method.

 In addition, the process of importing demand planning forecasts into the Master Schedule Level 1 is specially managed when the forecast time period overlaps with the master schedule time fence dates. This unique handling ensures a smooth transition between planning or demand time fence dates and prevents an over-import of forecasts that could result in surplus supply. This is accomplished by assessing the forecast that was imported previously for the same period. A detailed explanation of this method is provided here in a subsequent section; Importing Demand Forecasts Overlapping the Master Schedule Time Fence Dates.

How the Starting and Ending Dates are Calculated

The Starting Date for each of the items below is as follows:

The Ending Date is as follows:

How Each Distribution Method Imports the Forecast Quantity

The distribution method is one of the import parameters that you specify in the Import Demand Planning Forecasts assistant. The distribution method controls how the system distributes and displays the imported data.

Importing Demand Forecasts Overlapping the Master Schedule Time Fence Dates

If the Copy Forecast Inside Planning Time Fence setting is enabled (set to True) in the Import Demand Planning Forecasts assistant, and considering the import starting date if an exported forecast time period overlaps with the DTF date, then the forecast quantity in that exported forecast time period(which corresponds with the DTF date) is compared against the existing total forecast of MS Level 1 forecast 0 column for the same period up to the DTF date. This assess if there is a surplus forecast quantity to be imported from the exported forecast time period. If this surplus forecast quantity is less than the proportionated forecast quantity for the remaining days, then only the surplus forecast quantity is imported after the DTF date according to the chosen forecast distribution, otherwise the proportionated forecast quantity is imported.

A similar mechanism is there if the Copy Forecast Inside Planning Time Fence setting is not enabled (set to False) in the Import Demand Planning Forecasts assistant. Here the surplus forecast quantity is calculated based on the exported forecast period that corresponds with the PTF date, against the existing total forecast of MS Level 1 Forecast 0 column for the same period up to the PTF date.

Let’s consider a scenario where we’re importing a forecast for a part planned by MS, from today to one year ahead with Copy Forecast Inside Planning Time Fence setting not enabled (set to False).

Assume that the forecast periods are in months on the Exported Forecasts page. Let the PFT date of the part be on the 15th day (Day 15) in the next month and the corresponding exported forecast time period, from the 1st day (Day 1) to the end of the month (Day 31), has a forecast quantity of 3,100 on the Exported Forecasts page. There is already an existing forecast of 1,000 on Day 1, and 1,500 on Day 10, in Master Schedule Level 1 Forecast 0 column, and it will not be changed during the import job because we have set the Copy Forecast Inside Planning Time Fence to false. Hence, the forecast will be imported and distributed from Day 16.

During the import job, the proportionated quantity and the surplus are calculated as follows:

Since the surplus (600) is less than the proportionated quantity (1,600), only the surplus forecast quantity (600) will be imported and distributed according to the forecast distribution method. In another instance, if there is no surplus (i.e., 0), no forecast will be imported for that specific period or if the surplus forecast quantity is greater than the proportionated quantity, then the proportionated quantity will be imported. Similar mechanism is there for importing forecast from the exported time period that corresponds to the DTF date when the Copy Forecast Inside Planning Time Fence setting is enabled (set to True).

This approach ensures a smooth transition from planning and demand time fence dates and prevents from over-importing of forecast which may lead to excess supply.

Import Forecast by Customer Dimension

You can import forecasts from Demand Planner to Master Scheduling by Customer Dimension, using the Import Demand Planning Forecasts assistant and selecting the Import Type to Into Customer Dimension.

Forecasts are imported from Exported Forecasts By Dimension page, based on the customer dimension (Customer, Customer Stat Group, Market, Region, District or Country) that has been defined in the Demand Planner flow. It is mandatory that the same dimension is selected on the Forecast By field on the Master Schedule Level 1 Part page, otherwise, forecasts will not be imported.

The forecasts will be imported to the Forecast by Customer Dimension page. However, since these forecasts are automatically aggregated, they will also appear as total forecasts in the Master Schedule by Part page.

Dates, calculations, and distribution described earlier in this document are also applicable for import by Customer Dimension.

Import by Customer Dimension is available only from Demand Planner, not from Customer Schedules or from MRP Spare Parts.